APNewsBreak: Feds say delay worsened oil spill

— Delays in Exxon Mobil Corp.’s response to a major pipeline break beneath Montana’s Yellowstone River made the spill far worse than it otherwise would have been, federal regulators said.

Department of Transportation investigators examining the spill said pipeline controllers in Houston could have reduced the volume of the 1,500-barrel spill by about two-thirds if they isolated the rupture as soon as problems emerged.

Instead, crude drained from the severed, 12-inch pipeline for another 46 minutes before a remote control valve near the river was finally closed.

The July 1, 2011, spill fouled 70 miles of the riverbank along the scenic Yellowstone.

A copy of the investigators’ report was provided to The Associated Press by the office of Montana U.S. Sen. Max Baucus.

The investigators’ report chalks up the immediate cause of the spill to floodwaters that undermined the pipeline and left it exposed. As debris washing downriver piled up on the line, the pressure on the increased and it broke.

Investigators said that if Exxon’s emergency procedures had called for the immediate closure of upstream valves, “the crude oil release volume would have been much less and the location of the release would have been identified far more quickly.”

The report also faulted Exxon for not having contingency plans in place to notify pipeline controllers that the Yellowstone was flooding.

Investigators, however, found little fault in the steps the company took in the lead-up to the spill.

Despite warnings from city officials in Laurel that the riverbank was eroding, Exxon continued to run crude beneath the Yellowstone after a survey found a section of pipeline leading away from the river was still buried more than 6 feet deep.

Exxon’s “field observations and their ... depth of cover survey took reasonable precautions to address the flooding of the Yellowstone River it the spring and early summer of 2011,” the investigators wrote.

The investigation into the spill remains open. Whether any violations occurred remains under review, said spokesman Damon Hill with the Department of Transportation’s Pipeline and Hazardous Materials Safety Administration.

Exxon Mobil spent $135 million on its response to the spill, including cleanup and repair work.

An Exxon spokeswoman said Wednesday the company still was analyzing the report.

“We will continue to work cooperatively with the (Pipeline and Hazardous Materials Safety Administration) on any follow up actions,” spokeswoman Rachael Moore said. She added that Exxon “is committed to learning from these events.”

Landowners along the river have sued the company saying it did not do enough to prevent the spill and should have shut down the line during flooding.

Text Only
News
Video
Raw: Widespread Destruction in Moore, Okla. Raw: Massive Funnel Clouds in Oklahoma Raw: Japan's WWII Atrocities Under Fire in Seoul Voters Could Elect LA's First Female Mayor Huge Tornado Kills Dozens Near Oklahoma City Raw: Rescuers Pull Tornado Survivors to Safety Oklahoma Gov: 'Hearts Are Broken' After Tornado Raw: Walking in a Flattened Okla. Neighborhood Raw: Rescue Workers Search Oklahoma School Raw: Witness Describes Scene After Okla. Tornado Raw: Aftermath of Massive Tornado in Oklahoma Raw: House Burns After Massive Oklahoma Tornado Raw: Tornado on the Ground in Oklahoma Split-second Choice Ended With NY Student Dead White House Backs 'Shield Law' for Media Wave of Attacks Kills Scores in Iraq Pug Life on Display at Wisconsin Festival Company Promises to Make All Snail Mail Digital Analyst: Tumblr Fills Void in Yahoo's Offerings
Facebook
Sports Tweets
  • Sports tweets

    Anonymous The Port Arthur News Tue, May 31
Community Calendar
Loading…
Events by eviesays.com